Installation
Underway – Erbil Steel Mill Cooling System (Iraq)
Site installation has started on the cooling water system
we manufactured for a steel rolling mill in Erbil.
Installation
of the equipment delivered to site is under way. Our team is on site providing
installation supervision and making sure the work follows the design and
quality requirements.
The
first stage focuses on the Ø2850 mm sand filters:
·
Setting the filter vessels and external piping
·
Installing the nozzle plates and internal
distribution piping
·
Loading the filter media
The
nozzle plate distributes water evenly across the filter bed during filtration
and backwash. As part of the supervision, equipment placement, connections and
internal fittings are checked step by step.
The
system covers three independent cooling circuits:
·
Thermex: 1,350 m³/h
·
Open circuit: 1,100 m³/h
·
Closed circuit: 750 m³/h
The
scope includes 11 × Ø2850 mm sand filters, mill scale settling basins, pump
groups and cooling towers. High-flow filtration removes mill scale and
suspended solids, protecting pumps, nozzles and rolling mill equipment.
Following installation, commissioning is planned in the coming months.
Related
news: Erbil Steel Mill Cooling Water System (Iraq) – manufacturing and shipment
Delivered
in collaboration with our strategic engineering partner, Aquamatch.