We renewed two wastewater lift stations on the Bayburt
University campus, achieving a 35% increase in pumping efficiency.
The
campus's two existing lift units failed frequently, caused wastewater overflows
and posed risks to hygiene and environmental health. We replaced them with
high-capacity, reliable stations that convey wastewater to the main collector
without interruption.
The
stations, at two different locations, were designed to match their capacity
requirements:
·
Two stations: 36 m³/h and 108 m³/h
·
Submersible wastewater pumps in a "2 duty +
1 standby" configuration at each station
·
Continuous operation at a 20 m pumping head
·
35% increase in pumping efficiency
The
soft, slippery ground on site posed a serious risk of collapse during deep
excavation. Our site team carried out excavation and installation safely,
applying geotechnical measures and appropriate construction techniques.
With
the renewed stations, wastewater-related overflows and flooding on campus have
been eliminated; wastewater is now collected and conveyed to the main sewer
system through modern, reliable infrastructure. The project demonstrates our
ability to manage and deliver infrastructure projects under challenging site
conditions.